Street Project Status Expected Completion
Adam Lane Sidewalk In progress - contractor:   Mass Pavement Reclamation Early November 2014
Curbing In progress - contractor:   Mass Pavement Reclamation Late October/early November 2014
Final 1.5-inch overlay Waiting for contractor - T.L. Edwards Late October/early November 2014
Pondbrook Drive Sidewalk In progress - contractor:   Mass Pavement Reclamation Early November 2014
Curbing In progress - contractor:   Mass Pavement Reclamation Late October/early November 2014
Final 1.5-inch overlay Waiting for contractor - T.L. Edwards Late October/early November 2014
Great Rock Road Curbing In progress - contractor:   Mass Pavement Reclamation Late October/early November 2014
Install 2 handicap Ramps In progress - contractor:   Mass Pavement Reclamation Early November 2014
Final 1.5-inch overlay Waiting for contractor - T.L. Edwards Late October/early November 2014
Shingle MillLane Sidewalk In progress - contractor:   Mass Pavement Reclamation Early November 2014
Final 1.5-inch overlay Waiting for contractor - T.L. Edwards Late October/early November 2014
Hackett's Pond Drive Sidewalk In progress - contractor:   Mass Pavement Reclamation Early November 2014
Final 1.5-inch overlay Waiting for contractor - T.L. Edwards Late October/early November 2014
Old Icehouse Lane Final 1.5-inch overlay Waiting for contractor - T.L. Edwards Late October/early November 2014
Wade Way Final 1.5-inch overlay Waiting for contractor - T.L. Edwards Late October/early November 2014
Hearthstone Lane Final 1.5-inch overlay Waiting for contractor - T.L. Edwards Late October/early November 2014
Fieldstone Lane Pave 2 handicap ramps In Progress -  contractor:   Robert B. Our Late October 2014
2-inch overlay Waiting for contractor - T.L. Edwards Late October/early November 2014
Cobblestone Lane Pave 2 handicap Ramps In Progress -  contractor:   Robert B. Our Late October 2014
2-inch overlay Waiting for contractor - T.L. Edwards Late October/early November 2014
Broadway (Rte 53 to Norwell Line) Final 1.5-inch overlay Waiting for contractor - T.L. Edwards Late October/early November 2014
Larchmont/Birchwood/Maplewood Additional sidewalk work In Progress -  contractor:   Robert B. Our Late October 2014
Loam and seed shoulders In Progress -  contractor:   Robert B. Our Late October 2014
Driveway approaches In Progress -  contractor:   Robert B. Our Late October 2014
Final 1.5-inch overlay Waiting for contractor - T.L. Edwards Late October/early November 2014