Street | Project | Status | Expected Completion |
Adam Lane | Sidewalk | In progress - contractor: Mass Pavement Reclamation | Early November 2014 |
Curbing | In progress - contractor: Mass Pavement Reclamation | Late October/early November 2014 | |
Final 1.5-inch overlay | Waiting for contractor - T.L. Edwards | Late October/early November 2014 | |
Pondbrook Drive | Sidewalk | In progress - contractor: Mass Pavement Reclamation | Early November 2014 |
Curbing | In progress - contractor: Mass Pavement Reclamation | Late October/early November 2014 | |
Final 1.5-inch overlay | Waiting for contractor - T.L. Edwards | Late October/early November 2014 | |
Great Rock Road | Curbing | In progress - contractor: Mass Pavement Reclamation | Late October/early November 2014 |
Install 2 handicap Ramps | In progress - contractor: Mass Pavement Reclamation | Early November 2014 | |
Final 1.5-inch overlay | Waiting for contractor - T.L. Edwards | Late October/early November 2014 | |
Shingle MillLane | Sidewalk | In progress - contractor: Mass Pavement Reclamation | Early November 2014 |
Final 1.5-inch overlay | Waiting for contractor - T.L. Edwards | Late October/early November 2014 | |
Hackett's Pond Drive | Sidewalk | In progress - contractor: Mass Pavement Reclamation | Early November 2014 |
Final 1.5-inch overlay | Waiting for contractor - T.L. Edwards | Late October/early November 2014 | |
Old Icehouse Lane | Final 1.5-inch overlay | Waiting for contractor - T.L. Edwards | Late October/early November 2014 |
Wade Way | Final 1.5-inch overlay | Waiting for contractor - T.L. Edwards | Late October/early November 2014 |
Hearthstone Lane | Final 1.5-inch overlay | Waiting for contractor - T.L. Edwards | Late October/early November 2014 |
Fieldstone Lane | Pave 2 handicap ramps | In Progress - contractor: Robert B. Our | Late October 2014 |
2-inch overlay | Waiting for contractor - T.L. Edwards | Late October/early November 2014 | |
Cobblestone Lane | Pave 2 handicap Ramps | In Progress - contractor: Robert B. Our | Late October 2014 |
2-inch overlay | Waiting for contractor - T.L. Edwards | Late October/early November 2014 | |
Broadway (Rte 53 to Norwell Line) | Final 1.5-inch overlay | Waiting for contractor - T.L. Edwards | Late October/early November 2014 |
Larchmont/Birchwood/Maplewood | Additional sidewalk work | In Progress - contractor: Robert B. Our | Late October 2014 |
Loam and seed shoulders | In Progress - contractor: Robert B. Our | Late October 2014 | |
Driveway approaches | In Progress - contractor: Robert B. Our | Late October 2014 | |
Final 1.5-inch overlay | Waiting for contractor - T.L. Edwards | Late October/early November 2014 |